Laser Links
1GB Laser Link installed at Downs School, Compton. After a bulldozer managed to break an existing buried fibre optic at the school we were asked to come to access the damage and price the repair work. The fibre optic being some 400 to 500 metres long and mainly externally routed would have cost in excess of £10,000 in ground works to route the fibre before we had even started to install the new cable. We advised them that a laser link would effectivly give them the solution that they required for around half the cost of replacing the fibre optic cable. Also the cable and new duct working required would have taken weeks to complete. The new laser link had the school back up and running within a week.